Day 1
Excavation Completed
Pool Arrives
Pool Flipped – Ready for Installation
Pool Lifted to Set Into Excavation
Pool set and Leveled
Day 2
Flowable Fill Placed Around Pool and Water Added
Finish Backfilling with Flowable Fill
Day 3
Deck is Formed
Day 4
Deck is Poured
Day 5
Deck is Finished with Grading